TRISO-X TX-1 fuel plant

by X-energyUS

Make the pebble fuel X-energy's Xe-100 reactors run on, starting with Dow's Long Mott plant. Without its own licensed HALEU fuel factory, X-energy's reactor order book would have no fuel.

PilotStage 3 of 5

Shell complete (Sept 2026); interior and fuel equipment going in; 40-year NRC licence held.

Updated 13 Feb 2026Checked 11 Oct0 updates this week

Milestones

Next · Interior build-out and fuel equipment installation
  1. Licence application filed with the NRC6 Apr 2022Complete.
  2. Groundbreaking in Oak Ridge (then called TF3)13 Oct 2022Complete.
  3. Vertical construction begins17 Nov 2025Complete.
  4. NRC issues 40-year HALEU fuel licence13 Feb 2026Complete.
  5. Building shell complete24 Sep 2026+3 mooriginally Jun 2026Complete.
  6. Interior build-out and fuel equipment installationNowCurrent milestone.
  7. NRC readiness inspection, then fuel productionTarget 2027+24 mooriginally 2025Not yet reached.

Most important updates

Upcoming

  1. 2027NRC readiness inspection, then fuel production+24 mooriginally 2025 (next)