Milestones
- Licence application filed with the NRC6 Apr 2022Complete.
- Groundbreaking in Oak Ridge (then called TF3)13 Oct 2022Complete.
- Vertical construction begins17 Nov 2025Complete.
- NRC issues 40-year HALEU fuel licence13 Feb 2026Complete.
- Building shell complete24 Sep 2026+3 mo
originally Jun 2026Complete. - Interior build-out and fuel equipment installationNowCurrent milestone.
- NRC readiness inspection, then fuel productionTarget 2027+24 mo
originally 2025Not yet reached.
Most important updates
Upcoming
- 2027NRC readiness inspection, then fuel production+24 mo
originally 2025(next)