Cascade Advanced Energy Facility (Energy Northwest)

by X-energyUS

Build 320 MW from four Xe-100 reactors first, with the option to grow to 960 MW, as part of Amazon's aim for more than 5 GW of new US nuclear by 2039.

ResearchStage 1 of 5

In design with Cascade Nuclear Partners; NRC construction permit filing aimed at first half of 2027.

Updated 13 Aug 2026Checked 11 Oct0 updates this week

Milestones

Next · Construction permit application to the NRC
  1. Amazon invests in X-energy; Energy Northwest project agreed16 Oct 2024Complete.
  2. Name and design revealed; plan grows to 12 reactors (960 MW)Oct 2025Complete.
  3. Cascade Nuclear Partners chosen as design-builder23 Oct 2025Complete.
  4. Construction permit application to the NRCTarget 2027Current milestone.
  5. Site construction beginsNot yet reached.
  6. First phase (4 units) operatingNot yet reached.