Boom launches Superpower data-center turbines with a Crusoe order and $300M in new funding
Boom announced Superpower, a 42-megawatt natural-gas turbine derived from its Symphony supersonic engine, designed for AI data centers facing grid power shortages. Crusoe ordered 29 Superpower units—1.21 gigawatts of capacity—and Boom raised $300 million, stating it is now self-funded for both Superpower and its Overture supersonic airliner.
- 42-megawatt natural-gas turbine derived from Symphony supersonic engine.
- Maintains full capacity above 110°F without water cooling.
- Crusoe order: 29 units = 1.21 gigawatt total capacity.
- $300M funding from Darsana, Altimeter, ARK Invest, Bessemer, Robinhood, Y Combinator.