Revolution Wind

by ØrstedDK

Bring offshore wind power to southern New England, enough for about 350,000 homes, and prove US projects can be finished despite federal stop-work orders.

DeployStage 4 of 5

Power flowing since March 2026; all 65 turbines in by Sep 2026; full operation due end of 2026.

Updated 23d agoChecked 11 Oct0 updates this week

Milestones

Next · Full commercial operation
  1. Federal construction approval (BOEM record of decision)22 Aug 2023Complete.
  2. First turbine installedSep 2024Complete.
  3. First federal stop-work order; court lifts it a month later22 Aug 2025Complete.
  4. Second stop-work order; injunction granted 12 Jan 202622 Dec 2025Complete.
  5. First power to the New England grid13 Mar 2026Complete.
  6. Full commercial operationTarget Q4 2026+21 mooriginally 2025Current milestone.