StoryManufacturing

All 65 turbines installed at Revolution Wind

ØrstedRevolution Wind

The last of Revolution Wind's 65 Siemens Gamesa 11 MW turbines was installed, two years after the first one went up. Commissioning continues, and full commercial operation is expected in late 2026.

  • 65 Siemens Gamesa SG 11.0-200 DD turbines, 704 MW in total.
  • 400 MW is sold to Rhode Island and 304 MW to Connecticut.
  • First foundation went in May 2024, first turbine in September 2024.
  • Commercial operation, first planned for 2025, is now expected later in 2026.
Read the original · Press