Coastal Virginia Offshore Wind (CVOW)Dominion Energy—Federal judge grants Dominion an injunction; CVOW construction resumesCoastal Virginia Offshore Wind (CVOW)Dominion Energy—Dominion pushes CVOW's final turbine to end of 2027; cost estimate rises to about $11.65BCoastal Virginia Offshore Wind (CVOW)Dominion Energy—Interior Department orders a 90-day halt to offshore work on CVOW; Dominion suesCoastal Virginia Offshore Wind (CVOW)Dominion Energy—Coastal Virginia Offshore Wind sends its first power to the grid

Coastal Virginia Offshore Wind (CVOW)

by Dominion EnergyUS

Supply Virginia with up to 9.5 million MWh of power a year from offshore wind, avoiding up to 5 million tons of CO2 a year.

DeployStage 4 of 5

Delivering power since March 2026; about 81% complete with 31 turbines up (Jul 2026); last turbine end-2027.

Updated 31 Jul 2026Checked 11 Oct0 updates this week

Milestones

Next · Final (176th) turbine installed
  1. Two 6 MW pilot turbines running in federal waters2020Complete.
  2. Federal approval of the construction and operations planJan 2024Complete.
  3. All 176 turbine foundations installedSep 2025Complete.
  4. Work resumes after court lifts federal stop-work order16 Jan 2026Complete.
  5. First power delivered to the gridMar 2026Complete.
  6. Final (176th) turbine installedTarget Q4 2027+12 mooriginally Q4 2026Current milestone.