Lubiatowo-Kopalino nuclear plant

by Polskie Elektrownie JądrowePL

Give coal-heavy Poland a large, steady source of low-carbon power, with the first of three reactors on the grid in 2036.

PilotStage 3 of 5

Site cleared by regulator; licence application filed Mar 2026; EPC signing due end of 2026.

Updated 18d agoChecked 11 Oct0 updates this week

Milestones

Next · EPC contract signed
  1. Westinghouse AP1000 chosen for the first plantNov 2022Complete.
  2. Engineering services contract with Westinghouse and BechtelSep 2023Complete.
  3. EU approves state aid package9 Dec 2025Complete.
  4. Construction licence application filed31 Mar 2026Complete.
  5. EPC contract signedTarget Q4 2026Current milestone.
  6. First nuclear concreteTarget Q4 2028Not yet reached.
  7. Unit 1 in commercial operationTarget 2036+36 mooriginally 2033Not yet reached.