Milestones
- Westinghouse AP1000 chosen for the first plantNov 2022Complete.
- Engineering services contract with Westinghouse and BechtelSep 2023Complete.
- EU approves state aid package9 Dec 2025Complete.
- Construction licence application filed31 Mar 2026Complete.
- EPC contract signedTarget Q4 2026Current milestone.
- First nuclear concreteTarget Q4 2028Not yet reached.
- Unit 1 in commercial operationTarget 2036+36 mo
originally 2033Not yet reached.
Most important updates
- PEJ and Westinghouse-Bechtel agree main terms of the EPC contract; signing targeted for end of 202618d ago
- Polish regulator approves the Lubiatowo-Kopalino site as safe for a nuclear plant8 May 2026
- PEJ files the construction licence application for Poland's first nuclear plant; first unit targeted for 203631 Mar 2026
- European Commission approves Poland's state aid for its first nuclear plant: PLN 60B equity, full debt guarantees, 40-year price contract9 Dec 2025
- PEJ gets permit to start preparatory works on 330 hectares at the Lubiatowo-Kopalino nuclear site2 Sep 2025
Upcoming
- Q4 2026EPC contract signed (next)
- Q4 2028First nuclear concrete
- 2036Unit 1 in commercial operation+36 mo
originally 2033