Dominion pushes CVOW's final turbine to end of 2027; cost estimate rises to about $11.65B
Dominion EnergyCoastal Virginia Offshore Wind (CVOW)
With its second-quarter results Dominion said CVOW was about 81% complete with 31 turbines installed, delivering more than 450 MW. It moved the last turbine to the end of 2027, citing weather, vessel maintenance, loading and longer jacking work, and said tariffs had added about $800M.
- Tariffs added about $580M in Q1 and $230M in Q2 2026.
- Total project cost now about $11.65B.
- 31 turbines installed, more than 450 MW, as of 31 July 2026.
- CEO Bob Blue said the project's strategic value is unchanged.