Milestones
- Motor capacity investment starts (over $1B to date)2018Complete.
- About 13,000 motors built in the year2024Complete.
- 21-inch Navy second-stage motor static-fired, 10 months in21 Nov 2025Complete.
- Navy picks Northrop for 21-inch second stage: $94.3M, 60 unitsJan 2026Complete.
- $2B PAC-3 MSE motor and $1B THAAD framework agreements3 Aug 2026Complete.
- Elkton Propulsion Innovation Center opens10 Sep 2026Complete.
- Allegany tactical motor capability tripled (vs 2021)Target 2027Current milestone.
- Propellant capacity near 50 million lb a yearTarget 2028Not yet reached.
- Output above 25,000 motors a yearTarget 2029Not yet reached.
Most important updates
Upcoming
- 2027Allegany tactical motor capability tripled (vs 2021) (next)
- 2028Propellant capacity near 50 million lb a year
- 2029Output above 25,000 motors a year