Milestones
- NRC Environmental Review signed off30 Aug 2024Complete.
- Construction permit issued by NRC21 Nov 2024Complete.
- Groundbreaking at Oak Ridge17 Apr 2026Complete.
- Samsung C&T strategic partnership and investment agreement21 Sep 2026Complete.
- Power delivery to TVA gridTarget 2030Not yet reached.
Most important updates
- Samsung C&T invests $100 million in Kairos Power and joins EPC team for Hermes 220d ago
- Kairos Power Engineering Test Unit 3 completes Phase 1, validating Hermes 2 design features4 Sep 2026
- Kairos Power breaks ground on Hermes 2 demonstration plant at Oak Ridge Gaseous Diffusion Plant17 Apr 2026
- Kairos Power, Google, and TVA announce power purchase agreement for Hermes 2 to deliver 50 MW to Google data centers18 Aug 2025
Upcoming
- 2026First commercial-scale TRISO fuel production at BWXT (next)
- 2030Power delivery to TVA grid