General Matter submitted a 1,000-plus page application to the NRC for its Paducah plant, covering safety analysis, environment, fire hazards, decommissioning funding, security and emergency plans. It applies first for LEU and will file a HALEU amendment next year, to let construction start sooner. Clearing, earthworks and utilities are already under way.

  • Filed under 10 CFR Part 70; more than 1,000 pages.
  • Split licensing: LEU now, HALEU amendment in 2027.
  • Company aims for commercial-scale enrichment by the end of the decade.
  • Pre-construction site work has started.