Paducah enrichment plant

by General MatterUS

Make HALEU, the 5-20% enriched uranium most advanced reactors need, in the US at commercial scale. Almost all of it has come from Russia, whose supply ends under a 2028 import ban.

ProtoStage 2 of 5

NRC application filed Sept 2026; site prep under way; $900M DOE HALEU task order.

Updated 13d agoChecked 11 Oct0 updates this week

Milestones

Next · Licence amendment for HALEU
  1. DOE picks General Matter as one of four HALEU enrichersOct 2024Complete.
  2. Emerges from stealth; about $50M Series AApr 2025Complete.
  3. Signs DOE lease for 100 acres at PaducahAug 2025Complete.
  4. DOE awards a $900M HALEU task order5 Jan 2026Complete.
  5. NRC licence application filed (LEU)28 Sep 2026Complete.
  6. Licence amendment for HALEUTarget 2027Not yet reached.
  7. Commercial-scale enrichment beginsTarget 2030Not yet reached.

Most important updates

Upcoming

  1. 2027Licence amendment for HALEU (next)
  2. 1 Jan 2028US waivers for Russian enriched uranium end
  3. 2030Commercial-scale enrichment begins