Milestones
- Shidaowan unit 1 construction start19 Jun 2019Complete.
- Shidaowan unit 2 construction start21 Apr 2020Complete.
- Unit 1 connected to the grid31 Oct 2024Complete.
- Unit 2 connected to the gridSep 2025Complete.
- First two series units at Laiyang approved31 Jul 2026Complete.
- Laiyang site works under wayTarget 1 Sep 2026Current milestone.
Most important updates
Upcoming
- 1 Sep 2026Laiyang site works under way (next)