Dukovany 5 and 6 (APR1000)

by Korea Hydro & Nuclear PowerKR

Deliver two APR1000 reactors to the Czech grid, establishing Korea as a major European nuclear supplier.

ProtoStage 2 of 5

Conceptual design submitted April 2026. Site surveys ongoing. Construction starts 2029.

Updated Apr 2026Checked 11 Oct0 updates this week

Milestones

Next · Licensing and detailed design phase
  1. Contract awarded to KHNP consortium2023Complete.
  2. Final contract signed4 Jun 2025Complete.
  3. Extensive geological survey completed (13 km of exploratory wells)Apr 2026Complete.
  4. Conceptual design submitted to Czech regulatorsApr 2026Complete.
  5. Licensing and detailed design phaseTarget 2026Current milestone.
  6. Construction beginsTarget 2029Not yet reached.
  7. First reactor commissioning (Unit 5)Target 2036Not yet reached.
  8. Second reactor commissioning (Unit 6)Target 2038Not yet reached.

Most important updates

Upcoming

  1. 2026Licensing and detailed design phase (next)
  2. 2026Archaeological survey completion
  3. Q4 2026Cooling tower tender
  4. 2028Czech regulatory approval of detailed design
  5. 2029Construction begins
  6. 2036First reactor commissioning (Unit 5)
  7. 2038Second reactor commissioning (Unit 6)