Milestones
- Contract awarded to KHNP consortium2023Complete.
- Final contract signed4 Jun 2025Complete.
- Extensive geological survey completed (13 km of exploratory wells)Apr 2026Complete.
- Conceptual design submitted to Czech regulatorsApr 2026Complete.
- Licensing and detailed design phaseTarget 2026Current milestone.
- Construction beginsTarget 2029Not yet reached.
- First reactor commissioning (Unit 5)Target 2036Not yet reached.
- Second reactor commissioning (Unit 6)Target 2038Not yet reached.
Most important updates
Upcoming
- 2026Licensing and detailed design phase (next)
- 2026Archaeological survey completion
- Q4 2026Cooling tower tender
- 2028Czech regulatory approval of detailed design
- 2029Construction begins
- 2036First reactor commissioning (Unit 5)
- 2038Second reactor commissioning (Unit 6)