Milestones
- 37 electrolyzer modules installed from thyssenkrupp nuceraApr 2026Complete.
- Commissioning of electrolyzer and DRI plantTarget 2026Current milestone.
- First green steel production (first steel)Target 2027Not yet reached.
- Ramp to 2.4 million tonnes/yearTarget 2028Not yet reached.
- Full capacity of 5 million tonnes/yearTarget 2030Not yet reached.
Most important updates
Upcoming
- 2026Commissioning of electrolyzer and DRI plant (next)
- 2027First green steel production (first steel)
- 2028Ramp to 2.4 million tonnes/year
- 2030Full capacity of 5 million tonnes/year