Milestones
- Hyperion project announced2025Complete.
- First 2 GW target announced2025Complete.
- $27B financing joint venture with Blue Owl21 Oct 2025Complete.
- Expansion to 5 GW announced13 Jul 2026Complete.
- First 2 GW operationalTarget 2030Not yet reached.
- Full 5 GW operationalTarget 2032Not yet reached.
- Campus completionTarget 2036Not yet reached.
Most important updates
- Meta expands Hyperion, lifting total planned investment above $50B13 Jul 2026
- Meta and Blue Owl form a $27B joint venture to build and own the Hyperion campus21 Oct 2025
- Louisiana regulators approve Entergy's plan for new gas plants to power Hyperion20 Aug 2025
- Meta announces a multi-billion-dollar AI data centre in Richland Parish, Louisiana, later named Hyperion4 Dec 2024
Upcoming
- 2030First 2 GW operational (next)
- 2032Full 5 GW operational
- 2036Campus completion