Stibnite Gold-Antimony Project

by Perpetua ResourcesUS

Give the US a domestic antimony supply for munitions, batteries and industry after China cut exports, while producing about 300,000 oz of gold a year to pay for it.

PilotStage 3 of 5

Early construction since Oct 2025; $2.9B EXIM loan to close and final decision due Q4 2026.

Updated 31 Aug 2026Checked 11 Oct0 updates this week

Milestones

Next · EXIM loan closes; final investment decision
  1. US Forest Service Record of Decision approves mine plan3 Jan 2025Complete.
  2. Early works construction beginsOct 2025Complete.
  3. EXIM board approves $2.9B loan21 May 2026Complete.
  4. Antimony trisulfide plant opens at Idaho National Laboratory29 Jul 2026Complete.
  5. US District Court affirms federal approvals18 Aug 2026Complete.
  6. EXIM loan closes; final investment decisionTarget Q4 2026Current milestone.
  7. First production after about three years of constructionTarget 2029Not yet reached.