Clarksville cathode plant (NCMA)

by LG ChemKR

Localise North American battery cathode supply and prove economies at scale, supporting North American EV production and reducing Asia-supply dependence.

ProtoStage 2 of 5

Under construction in Tennessee. Start-up 2026 with flexible timing based on customer demand.

Updated Jan 2026Checked 11 Oct0 updates this week

Milestones

Next · Start-up and production ramp
  1. Site acquisition and planning2022Complete.
  2. GM 950 kt supply agreement2022Complete.
  3. Ground breaking ceremonyDec 2023Complete.
  4. Toyota €2.02B cathode supply agreementOct 2023Complete.
  5. Start-up and production rampTarget 2026Current milestone.
  6. Full 60 kt/yr productionTarget 2027Not yet reached.