Milestones
- SG 14-236 DD prototype assembly beginsOct 2022Complete.
- Blade production begins at Aalborg facilityApr 2022Complete.
- Prototype installed at Østerild test centerFeb 2023Complete.
- Prototype delivers power to gridMar 2023Complete.
- Commercial availability / type certification2024Complete.
- First turbine installed at Thor wind farm (Denmark)Mar 2026Complete.
- 36 of 72 turbines installed at Thor (Denmark)Jul 2026Complete.
- All 66 turbines installed at Greater Changhua (Taiwan)Jan 2026Complete.
- Thor (Denmark) full commissioning by spring 2027Target 2027Current milestone.
- Baltica 2 (Poland) commissioningTarget 2027Not yet reached.
- Greater Changhua (Taiwan) full operationTarget Q3 2026Not yet reached.
Most important updates
- Thor wind farm reaches 50% turbine installation milestone17 Jul 2026
- First SG 14-236 DD turbine installed at Thor offshore wind farm (Denmark)4 Mar 2026
- All 66 SG 14-236 DD turbines installed at Greater Changhua (Taiwan)20 Jan 2026
- Siemens Gamesa SG 14-236 DD prototype delivers power to the grid23 Mar 2023
- Siemens Gamesa installs first 115-metre blade on SG 14-236 DD prototype at Østerild test center16 Feb 2023
Upcoming
- Q3 2026Greater Changhua (Taiwan) full operation (next)
- 2027Thor (Denmark) full commissioning by spring 2027
- 2027Baltica 2 (Poland) commissioning