Project Matador AP1000 Units 1-4

by Fermi AmericaUS

Restart large-reactor building in the US and give a private AI campus decades of steady, carbon-free power without relying on the public grid.

ProtoStage 2 of 5

Draft NRC environmental review (Oct 2026) gives a preliminary yes; final due Dec 2026, safety review ongoing.

Updated Mar 2026Checked 11 Oct0 updates this week

Milestones

Next · Safety evaluation and Commission licence decision
  1. First part of combined licence application submitted17 Jun 2025Complete.
  2. NRC accepts first two parts of the applicationSep 2025Complete.
  3. Picked for NRC fast-track environmental review; scoping opensMar 2026Complete.
  4. Draft environmental review; NRC staff preliminary yes9 Oct 2026Complete.
  5. Safety evaluation and Commission licence decisionNowCurrent milestone.
  6. Full nuclear construction startTarget 2027Not yet reached.

Most important updates

Upcoming

  1. 2027Full nuclear construction start (next)