Milestones
- First new cascade of the expansion starts producingMay 2025Complete.
- NRC approval to enrich up to 10% U-235 announced2 Oct 2025Complete.
- First US commercial LEU+ run, at 8.5% U-235Dec 2025Complete.
- Fourth new cascade: halfway through the 700,000 SWU programme30 Mar 2026Complete.
- New 2.1 million SWU plant announced, privately funded2 Jun 2026Complete.
- Fifth new cascade starts production22 Jun 2026Complete.
- Eighth and last cascade: 700,000 SWU addedTarget Q1 2027Current milestone.
- Refurbishment of existing cascades beginsTarget 2027Not yet reached.
- Construction of the new plant beginsTarget 2029Not yet reached.
- First production from the new plantTarget 2032Not yet reached.
- New plant fully built; site above 7 million SWU a yearTarget 2036Not yet reached.
Most important updates
- Fifth new cascade starts production at Urenco USA22 Jun 2026
- Urenco to build a 2.1 million SWU enrichment plant in New Mexico, lifting the site past 7 million SWU2 Jun 2026
- Urenco USA starts its fourth new cascade, halfway through a 700,000 SWU expansion2 Apr 2026
- Urenco USA brings its second new cascade online ahead of schedule10 Sep 2025
Upcoming
- Q1 2027Eighth and last cascade: 700,000 SWU added (next)
- 2027Refurbishment of existing cascades begins
- Q1 2027Last of eight new cascades online
- 1 Jan 2028US waivers for Russian enriched uranium end
- 2029Construction of the new plant begins
- 2032First production from the new plant
- 2036New plant fully built; site above 7 million SWU a year