Duane Arnold restart
Photo: Jssteinke · Public domain (opens commons.wikimedia.org)

Duane Arnold restart

by NextEra EnergyUS

Return about 615 MW of round-the-clock, carbon-free power to the Midwest grid years faster than any new reactor could be built.

PilotStage 3 of 5

$1.9B federal loan closed Sep 2026; NRC decisions possible from Jan 2028; restart targeted for Q1 2029.

Updated 8 Sep 2026Checked 11 Oct0 updates this week

Milestones

Next · NRC licensing decisions
  1. Plant shuts after derecho flattens its cooling towers10 Aug 2020Complete.
  2. Licensing request filed with NRC to restore operations29 Jan 2025Complete.
  3. Google 25-year power deal; NextEra to own 100%27 Oct 2025Complete.
  4. NRC draft finding of no significant environmental impact4 Aug 2026Complete.
  5. DOE closes $1.9B restart loan8 Sep 2026Complete.
  6. NRC licensing decisionsTarget Jan 2028Current milestone.
  7. Reactor back on the gridTarget Q1 2029+3 mooriginally Q4 2028Not yet reached.

Most important updates

Upcoming

  1. Q4 2026NRC final environmental assessment and finding of no significant impact (next)
  2. Jan 2028NRC licensing decisions
  3. Q1 2029Reactor back on the grid+3 mooriginally Q4 2028
  4. Q1 2029Duane Arnold returns to service