Milestones
- Begins HALEU enrichment operations; delivers initial 20 kg to DOEOct 2023Complete.
- Cumulative 1,900 kg HALEU delivered to DOE, demo phase completeJun 2025Complete.
- DOE issues $900 million task order for commercial expansionJul 2026Complete.
- Fluor appointed as EPC contractor for facility expansionFeb 2026Complete.
- Centrifuge manufacturing begins; first domestic centrifuges producedDec 2025Complete.
- First new large-scale enrichment capacity onlineTarget 2029Not yet reached.
- Achieve 12 metric tons HALEU per year productionTarget 2029Not yet reached.
Most important updates
- Centrus signs $900 million DOE task order for HALEU expansion; total potential value $1.07 billionJul 2026
- Fluor Corporation appointed as engineering, procurement and construction (EPC) contractor for Piketon expansionFeb 2026
- Centrus begins domestic centrifuge manufacturing in Oak Ridge to support Piketon expansionDec 2025
- Centrus completes Phase 2 HALEU delivery: 900 kg total produced under demonstration contractJun 2025
- Centrus begins HALEU enrichment operations at Piketon, marking first new U.S. uranium enrichment since 1954Oct 2023
Upcoming
- 2027Centrifuge manufacturing facility operational (next)
- 2029First new large-scale enrichment capacity online
- 2029Achieve 12 metric tons HALEU per year production
- 2029Advanced reactors enter service
- 2030Natrium deployment begins