Milestones
- Site selection announced in Peoria Innovation CoreNov 2023Complete.
- Land acquisition and site preparationAug 2025Complete.
- Phase 1 groundbreaking ceremony6 Oct 2025Complete.
- Phase 1 first manufacturing facility operationalTarget Jun 2027Not yet reached.
- Phase 1 production rampTarget Q1 2028Not yet reached.
- Phase 2 construction beginsTarget Q4 2027Not yet reached.
- Phase 2 construction completeTarget Q4 2029Not yet reached.
Most important updates
Upcoming
- Jun 2027Phase 1 first manufacturing facility operationalin about 33 weeks (next)
- Q4 2027Phase 2 construction begins
- Q1 2028Phase 1 production ramp
- Q4 2029Phase 2 construction complete