Arizona Advanced Packaging & TestAmkor Technology—TSMC and Amkor establish 10-year partnership for U.S. advanced packagingArizona Advanced Packaging & TestAmkor Technology—Amkor announces Phase 2 expansion to $12 billion as customer demand surpasses initial capacityArizona Advanced Packaging & TestAmkor Technology—Amkor acquires 67-acre adjacent parcel for Phase 2 campus expansion

Arizona Advanced Packaging & Test

by Amkor TechnologyUS

Build U.S. advanced packaging capacity for AI, HPC, mobile, automotive.

DeployStage 4 of 5

Phase 1 mid-2027, volume early 2028. Phase 2 late 2027–end 2029.

Updated 8 Sep 2026Checked 11 Oct0 updates this week

Milestones

Next · Phase 1 first manufacturing facility operational
  1. Site selection announced in Peoria Innovation CoreNov 2023Complete.
  2. Land acquisition and site preparationAug 2025Complete.
  3. Phase 1 groundbreaking ceremony6 Oct 2025Complete.
  4. Phase 1 first manufacturing facility operationalTarget Jun 2027Not yet reached.
  5. Phase 1 production rampTarget Q1 2028Not yet reached.
  6. Phase 2 construction beginsTarget Q4 2027Not yet reached.
  7. Phase 2 construction completeTarget Q4 2029Not yet reached.

Most important updates

Upcoming

  1. Jun 2027Phase 1 first manufacturing facility operationalin about 33 weeks (next)
  2. Q4 2027Phase 2 construction begins
  3. Q1 2028Phase 1 production ramp
  4. Q4 2029Phase 2 construction complete