ANKA-3

by Turkish Aerospace (TAI)TR

Give the Turkish Air Force a stealthy uncrewed aircraft that can strike defended targets and act as a wingman to the KAAN fighter, without risking a pilot.

PilotStage 3 of 5

Production version being built; first flight planned for early 2027, deliveries from the second half of 2027.

Updated 23 Aug 2026Checked 11 Oct0 updates this week

Milestones

Next · First flight of the production configuration
  1. First flight (70 minutes)28 Dec 2023Complete.
  2. First live-fire test with a guided bomb20 Sep 2024Complete.
  3. Critical design review complete; design frozenNov 2025Complete.
  4. Serial-production contract for 50+ signed at SAHA 2026 (reported)7 May 2026Complete.
  5. First flight of the production configurationTarget Q1 2027Current milestone.
  6. First deliveries to the Turkish Air Force (second half)Target 2027Not yet reached.
Primer