Milestones
- Member states release funds for preparatory workJul 2024Complete.
- €63M preparatory contract with OHB Italia17 Oct 2024Complete.
- Critical design review completed6 Feb 2026Complete.
- €81.2M build-and-test contract signed10 Feb 2026Complete.
- Build, assemble and test the spacecraftTarget 2027Current milestone.
- LaunchTarget Q2 2028Not yet reached.
- Arrive at ApophisTarget Feb 2029Not yet reached.
- Apophis passes 32,000 km from EarthTarget 13 Apr 2029Not yet reached.
Most important updates
Upcoming
- 2027Build, assemble and test the spacecraft (next)
- Q2 2028Launch
- Feb 2029Arrive at Apophis
- 13 Apr 2029Apophis passes 32,000 km from Earth