Milestones
- Selected as ESA's M3 science mission19 Feb 2014Complete.
- Industrial build starts with OHB as prime contractorOct 2018Complete.
- Ariane 6 launch contract signed29 Jan 2025Complete.
- Spacecraft completed with sunshield and solar panels9 Oct 2025Complete.
- Environmental tests finished (vibration, vacuum, EMC)Jul 2026Complete.
- Launch on Ariane 6 to Sun-Earth L2Target Mar 2027+5 mo
originally Q4 2026Current milestone.
Most important updates
- PLATO completes its last environmental tests; launch set for March 202720 Jul 2026
- PLATO passes thermal-vacuum tests in ESA's Large Space Simulator23 Apr 2026
- PLATO spacecraft completed with sunshield and solar panels, ready for final tests9 Oct 2025
- 24 of PLATO's 26 cameras installed on its optical bench at OHB8 May 2025
- ESA books Ariane 6 to launch PLATO, the rocket's first science mission and first trip to L229 Jan 2025
Upcoming
- Mar 2027Launch on Ariane 6 to Sun-Earth L2+5 mo
originally Q4 2026in about 20 weeks (next)