White Mesa heavy rare earth oxides

by Energy Fuels IncUS

Produce 35 t/yr dysprosium and 12 t/yr terbium oxide at 99.9% purity by late 2027 to early 2028.

ProtoStage 2 of 5

Pilot: 1 kg/wk terbium; Phase 1 upgrades July 2026; commercial by late 2027 to early 2028.

Updated Jul 2026Checked 11 Oct0 updates this week

Milestones

Next · Phase 1: Commercial Tb and Dy production ramp
  1. First kilogram of 99.9% terbium oxide producedMar 2026Complete.
  2. Nearly 30 kg of 99.9% dysprosium oxide produced (cumulative to date)Mar 2026Complete.
  3. Terbium production pilot rate reaches 1 kg/week2026Complete.
  4. Phase 1: Commercial Tb and Dy production rampTarget Q4 2027Not yet reached.
  5. Phase 1: Sm, Eu, Gd circuit expansionTarget Q1 2028Not yet reached.

Most important updates

Upcoming

  1. 2026US government critical mineral initiatives (next)
  2. Q4 2027Phase 1: Commercial Tb and Dy production ramp
  3. Q1 2028Phase 1: Sm, Eu, Gd circuit expansion