Virginia Titanium Manufacturing Campus

by IperionXUS

Commercial-scale titanium facility in South Boston, Virginia using HAMR to produce high-purity titanium metal and powder from scrap and ore concentrate.

DeployStage 4 of 5

Operating 24/7 on powder ramp-up. All systems commissioned Sept 2025. Target 200 tpa by end-2026.

Updated Jun 2026Checked 10 Oct0 updates this week

Milestones

Next · Achieve 200 tpa production rate
  1. First HAMR deoxygenation runAug 2024Complete.
  2. First end-to-end commercial cycleDec 2024Complete.
  3. All production systems fully commissionedSep 2025Complete.
  4. Achieve 200 tpa production rateTarget Dec 2026Current milestone.