Milestones
- Development permits received2023Complete.
- DFS commenced with US govt supportApr 2025Complete.
- DFS completed with $813M NPVJun 2026Complete.
- Mining and environmental permitsTarget 2027Current milestone.
- Mining and beneficiation ramp-upTarget 2028Not yet reached.
Most important updates
Upcoming
- 2027Mining and environmental permits (next)
- 2028Mining and beneficiation ramp-up
- 2028Mine and beneficiation plant construction