Milestones
- Pilot trial lifts 3,000+ t of nodules up a 4.3 km riserNov 2022Complete.
- Consolidated NOAA application (~65,000 km2) filedJan 2026Complete.
- NOAA: application in substantial compliance9 Mar 2026Complete.
- NOAA: consolidated application in full compliance28 Apr 2026Complete.
- Allseas development and production contract signed11 May 2026Complete.
- NOAA certification, environmental review and permit decisionTarget Oct 2026Current milestone.
- Collection system commissioning beginsTarget Q4 2027Not yet reached.
Most important updates
- NOAA opens 60-day public comment on TMC USA's commercial recovery application19 Aug 2026
- TMC signs contract with Allseas to build and run a 3 Mt/yr commercial nodule collection system11 May 2026
- NOAA finds TMC USA's consolidated 65,000 km2 nodule application in substantial compliance9 Mar 2026
- TMC and Allseas finish pilot trial: over 3,000 tonnes of nodules lifted from 4.3 km deep14 Nov 2022
Upcoming
- Oct 2026NOAA certification, environmental review and permit decision (next)
- 13 Oct 2026NOAA virtual public hearing on TMC USA application
- 19 Oct 2026Public comment period on the consolidated application closes
- Q4 2027Collection system commissioning begins