Milestones
- Phase 3 concentrator produces first concentrateJun 2024Complete.
- Seismic event floods eastern Kakula; mining haltedMay 2025Complete.
- Mining restarts on Kakula's western sideJun 2025Complete.
- First copper anodes from on-site smelterDec 2025Complete.
- 60 MW on-site solar and battery baseloadTarget Q3 2026Current milestone.
- Kakula stoping resumesTarget 2027Not yet reached.
- Smelter at full 500 kt/yr capacityTarget 2028Not yet reached.
- Copper output above 500,000 t/yrTarget 2028+12 mo
originally 2027Not yet reached.
Most important updates
- Ivanhoe tightens 2026 Kamoa-Kakula guidance to 290,000-310,000 t; smelter at about 60% capacity29 Jul 2026
- Kamoa-Kakula smelter, Africa's largest, produces its first copper anodes5 Jan 2026
- Ivanhoe sets 2026-27 Kamoa-Kakula guidance as dewatering advances and the smelter starts up3 Dec 2025
- Ivanhoe cuts 2025 Kamoa-Kakula guidance by 28% and withdraws 2026 target after seismic event floods Kakula11 Jun 2025
Upcoming
- Q3 202660 MW on-site solar and battery baseload (next)
- 2027Kakula stoping resumes
- Q1 2027Updated Kamoa-Kakula production guidance for 2027
- 2028Smelter at full 500 kt/yr capacity
- 2028Copper output above 500,000 t/yr+12 mo
originally 2027