Greenbushes lithium mine

by Talison LithiumAU

Expand spodumene concentrate capacity to meet growing global lithium demand for batteries and other applications, while managing ore grade decline.

ScalingStage 5 of 5

CGP3 ramp-up after June fire. FY2026 guidance 1.375–1.425 Mt concentrate. CGP4 starts 2027.

Updated Jun 2026Checked 11 Oct0 updates this week

Milestones

Next · CGP3 resume production
  1. Original mine opened1983Complete.
  2. CGP1 commissioned2012Complete.
  3. CGP2 commissioned2019Complete.
  4. CGP3 first ore feedDec 2025Complete.
  5. CGP3 fire and shutdownJun 2026Complete.
  6. CGP3 resume productionTarget Q3 2026Current milestone.
  7. CGP4 construction startsTarget 2027Not yet reached.

Most important updates

Upcoming

  1. Q3 2026CGP3 resume production (next)
  2. Q4 2026CGP3 reaches full capacity
  3. 2027CGP4 construction starts