The brief
- Ore grades nearly double industry average, lowering processing costs and tailings volumes.
- CGP3 added 500 kt/yr capacity with first ore in December 2025. CGP4 planned for 2027.
- Mine supplies over 20% of global lithium. Mine life approved until 2045.
Technical approach
Spodumene ore mining
Greenbushes mines spodumene, a lithium-bearing mineral. Ore grades are roughly double the global average, reducing energy cost per tonne.
Spodumene concentrate
Milled ore is separated by flotation to produce spodumene concentrate, the feedstock for lithium refiners.
Modular plant additions
Talison expands by adding discrete plants rather than reworking the entire mine, spreading investment and risk.