Columbia and Virginia submarine productionGeneral Dynamics Electric Boat—Navy awards $76.6B for nine Virginia-class and five Columbia-class submarinesColumbia and Virginia submarine productionGeneral Dynamics Electric Boat—Navy adds $2.3B to Electric Boat's Columbia contract as the lead boat slips to 2029Columbia and Virginia submarine productionGeneral Dynamics Electric Boat—Electric Boat reports 13% more submarine tonnage as supply chain stays the gating itemColumbia and Virginia submarine productionGeneral Dynamics Electric Boat—Pentagon's submarine chief says delivering the first Columbia in 2028 will be a heavy lift

Columbia and Virginia submarine production

by General Dynamics Electric BoatUS

Build one Columbia-class and two Virginia-class submarines a year, a rate US yards have never reached, so new missile subs replace Ohio-class boats that start retiring in 2027.

ScalingStage 5 of 5

Virginia at about 1.3 boats a year vs a goal of two; first Columbia due 2028 after slipping.

Updated 29 Jul 2026Checked 11 Oct0 updates this week

Milestones

Next · District of Columbia delivered
  1. Columbia-class construction begins1 Oct 2020Complete.
  2. District of Columbia (lead boat) keel laid4 Jun 2022Complete.
  3. Wisconsin (second Columbia) keel laidAug 2025Complete.
  4. $2.3B Columbia contract modificationNov 2025Complete.
  5. USS Idaho commissioned (Virginia class)Apr 2026Complete.
  6. $76.6B award: 9 Virginia + 5 Columbia boats29 Jul 2026Complete.
  7. District of Columbia deliveredTarget 2028+12 mooriginally 2027Current milestone.
  8. District of Columbia on first deterrent patrolTarget 2031Not yet reached.
  9. Wisconsin deliveredTarget 2032Not yet reached.
  10. Two Virginia-class boats a yearTarget 2032+48 mooriginally 2028Not yet reached.
  11. Groton (third Columbia) deliveredTarget 2034Not yet reached.

Most important updates

Upcoming

  1. 2028District of Columbia delivered+12 mooriginally 2027 (next)
  2. 2028District of Columbia (first Columbia-class) delivery
  3. 2031District of Columbia on first deterrent patrol
  4. 2032Wisconsin delivered
  5. 2032Two Virginia-class boats a year+48 mooriginally 2028
  6. 2032Wisconsin (second Columbia-class) delivery
  7. 2034Groton (third Columbia) delivered
Primer