Milestones
- Construction completedAug 2021Complete.
- Operating license grantedJun 2023Complete.
- First criticality achieved11 Oct 2023Complete.
- First thorium addition and fuel conversionOct 2024Complete.
- 100 MWt demonstration reactor plannedTarget 2035Not yet reached.
Most important updates
- SINAP announces first thorium-to-uranium conversion in molten salt reactor1 Nov 2025
- First thorium addition to TMSR-LF1; uranium-233 breeding achieved for the first timeOct 2024
- TMSR-LF1 achieves first criticality; first sustained nuclear reaction in Chinese molten salt reactor11 Oct 2023
- TMSR-LF1 receives operating license from China's Ministry of Ecology and EnvironmentJun 2023
- TMSR-LF1 reactor construction completed in Wuwei, Gansu ahead of original 2024 schedule2021
Upcoming
- 2030Ongoing fuel cycle and materials testing (next)
- 2035100 MWt demonstration reactor planned