SunZia Wind and Transmission

by Pattern EnergyUS

Deliver renewable power from a remote high-wind region to major load centers using long-distance HVDC transmission.

ScalingStage 5 of 5

Largest US wind farm; 916 turbines, 550-mile HVDC line. COD June 2026.

Updated Jun 2026Checked 11 Oct0 updates this week

Milestones

Next · Full 3.65 GW production and transmission
  1. SunZia project announcement and approvals2019Complete.
  2. Wind farm construction begins2023Complete.
  3. First turbine installed2024Complete.
  4. HVDC transmission line completed2025Complete.
  5. Commercial operation date (COD)Jun 2026Complete.
  6. Full 3.65 GW production and transmissionTarget Q3 2026Current milestone.

Most important updates

Upcoming

  1. Q3 2026Full 3.65 GW production and transmission (next)
  2. 2027Announcement of next multi-GW Pattern Energy project
  3. Q2 2027Expansion of SunZia transmission capacity