Kaleidos

by Radiant IndustriesUS

A 1 MWe high-temperature gas-cooled microreactor using TRISO fuel and helium cooling with passive emergency shutdown.

PilotStage 3 of 5

Shipped to INL's DOME in Aug 2026 for a five-phase test ending in a 150-hour full-power run; first commercial unit due 2028.

Updated 17 Dec 2025Checked 11 Oct0 updates this week

Milestones

Next · First commercial unit delivery
  1. Company founded2020Complete.
  2. Series B funding2022Complete.
  3. Series C fundingNov 2024Complete.
  4. Kaleidos shipped to INL12 Aug 2025Complete.
  5. Installation and criticality testingQ2 2026Complete.
  6. First commercial unit deliveryTarget 2028Not yet reached.