ITER (International Thermonuclear Experimental Reactor)

by ITER OrganizationFR

ProtoStage 2 of 5

Core assembly at halfway point. Deuterium-deuterium operation targeted for 2035.

Checked 10 Oct0 updates this week

Milestones

Next · Research operations phase (hydrogen and deuterium plasma)
  1. 5th vacuum vessel sector installed in tokamak pitMay 2026Complete.
  2. 6th vacuum vessel sector installedJul 2026Complete.
  3. Two-thirds of tokamak core installed (six of nine sectors)Jul 2026Complete.
  4. All core tokamak components on siteOct 2026Complete.
  5. Research operations phase (hydrogen and deuterium plasma)Target 2034Not yet reached.
  6. Deuterium-deuterium fusion operationTarget 2035Not yet reached.
  7. Deuterium-tritium operationsTarget 2039Not yet reached.

Upcoming

  1. 2034Research operations phase (hydrogen and deuterium plasma) (next)
  2. 2035Deuterium-deuterium fusion operation
  3. 2039Deuterium-tritium operations