Haliade-X Dogger Bank

by GE VernovaUS

Supply renewable electricity from offshore wind to 6 million UK homes annually.

DeployStage 4 of 5

Dogger Bank A complete; B & C installation ongoing through 2027.

Updated Feb 2026Checked 11 Oct0 updates this week

Milestones

Next · Dogger Bank B turbine installation
  1. Haliade-X selected for Dogger Bank2021Complete.
  2. Blade factory announced in northeast England2023Complete.
  3. Dogger Bank A and B turbine installation begins2025Complete.
  4. Dogger Bank A turbine installation completeFeb 2026Complete.
  5. Dogger Bank B turbine installationTarget 2026Current milestone.
  6. Dogger Bank B commissioningTarget Q2 2027Not yet reached.
  7. Dogger Bank C turbine installationTarget 2027Not yet reached.

Most important updates

Upcoming

  1. 2026Dogger Bank B turbine installation (next)
  2. 2027Dogger Bank C turbine installation
  3. Q2 2027Dogger Bank B commissioning
  4. Q4 2027Dogger Bank C operation