Geretsried Commercial Facility

by Eavor TechnologiesCA

First commercial Eavor-Loop with four closed-loop systems at 4.5 km depth. Designed for 64 MWth thermal and 8.2 MWe electrical output.

DeployStage 4 of 5

Electricity to grid December 2025; encountered loop clogging mid-2026.

Updated Dec 2025Checked 10 Oct0 updates this week

Milestones

No announced next step
  1. Drilling beginsJul 2023Complete.
  2. First loop partial operation (heating)Oct 2024Complete.
  3. First electricity to gridDec 2025Complete.
  4. All four loops operational at full capacityMissed · Aug 2026Missed.
Primer