Milestones
- Drilling beginsJul 2023Complete.
- First loop partial operation (heating)Oct 2024Complete.
- First electricity to gridDec 2025Complete.
- All four loops operational at full capacityMissed · Aug 2026Missed.
Most important updates
- Eavor's Geretsried facility delivers first grid electricity from closed-loop geothermal systemDec 2025
- First Eavor-Loop at Geretsried begins supplying heat to district heating network in GermanyOct 2024
- Eavor Technologies begins drilling at Geretsried, Germany for first commercial closed-loop geothermal facilityJul 2023