EPR2 Programme

by EDFFR

Replace aging French reactors and meet EU decarbonization targets while establishing domestic nuclear reactor manufacturing and supply chains.

ProtoStage 2 of 5

FID targeted end-2026, construction begins 2027, first unit Penly commissioned 2038.

Updated Aug 2026Checked 11 Oct0 updates this week

Milestones

Next · Final investment decision
  1. Preparatory works at Penly begin2024Complete.
  2. Government authorization for Gravelines site preparationsAug 2026Complete.
  3. Final investment decisionTarget Dec 2026Not yet reached.
  4. Construction beginsTarget 2027Not yet reached.
  5. First EPR2 at Penly commissionedTarget 2038+36 mooriginally 2035Not yet reached.
  6. Subsequent units commissioned (Penly, Gravelines, Bugey)Target 2039Not yet reached.

Most important updates

Upcoming

  1. Dec 2026Final investment decisionin about 7 weeks (next)
  2. 2027Construction begins
  3. 2027First concrete pour at Penly
  4. 2038First EPR2 at Penly commissioned+36 mooriginally 2035
  5. 2039Subsequent units commissioned (Penly, Gravelines, Bugey)