Milestones
- Construction starts (RMB 40B project)Oct 2023Complete.
- Phase 1 (320,000 t/yr) officially starts productionJul 2025Complete.
- First ISCC PLUS green ammonia certificationJul 2025Complete.
- First commercial export cargo, to South Korea26 Feb 2026Complete.
- Capacity expansion toward 1.5 Mt/yrTarget 2028Not yet reached.
Most important updates
- Envision ships the first commercial green ammonia cargo, from Chifeng to LOTTE Fine Chemical in South Korea26 Feb 2026
- Chifeng becomes the first project to earn ISCC PLUS green ammonia certification17 Jul 2025
- Envision's off-grid Chifeng plant officially starts producing green ammonia at 320,000 t a year11 Jul 2025
- Envision breaks ground on its RMB 40 billion Chifeng green hydrogen and ammonia project22 Oct 2023
Upcoming
- 2028Capacity expansion toward 1.5 Mt/yr (next)