Carrington Liquid Air Storage Plant

by Highview PowerGB

PilotStage 3 of 5

Stability island operational August 2026. Full LAES system targeted for 2027.

Updated Jun 2024Checked 10 Oct0 updates this week

Milestones

Next · Stability island operational
  1. Funding secured from UKIB, Centrica, syndicateJun 2024Complete.
  2. Construction beginsQ3 2024Complete.
  3. Stability island operationalTarget Aug 2026Not yet reached.
  4. Full LAES system operationalTarget 2027Not yet reached.

Most important updates

Upcoming

  1. Aug 2026Stability island operational (next)
  2. 2027Full LAES system operational