DeployStage 4 of 5

Under construction at Darlington (2029); US permit at Clinch River (Sept 2026).

Updated 11d agoChecked 10 Oct0 updates this week

Milestones

Next · First BWRX-300 operational at Darlington
  1. Ontario and OPG approve construction at DarlingtonMay 2025Complete.
  2. Basemat set at Darlington22 Apr 2026Complete.
  3. NRC issues construction permit for Clinch River to TVA30 Sep 2026Complete.
  4. First BWRX-300 operational at DarlingtonTarget 2029Not yet reached.
  5. Four units operational at DarlingtonTarget Q4 2030Not yet reached.

Most important updates

Upcoming

  1. Q1 2027Clinch River construction begins (next)
  2. 2029First BWRX-300 operational at Darlington
  3. Q4 2030Four units operational at Darlington