Milestones
- Construction beginsJan 2023Complete.
- Main building completed, full-scale assembly beginsMay 2025Complete.
- Roof slab pouring completedMar 2025Complete.
- Dewar base installation (main machine's first component)Oct 2025Complete.
- Campus delivered early and put into useJun 2026Complete.
- Main machine enters four-ring assemblyTarget Oct 2026Current milestone.
- First plasmaTarget Q4 2027Not yet reached.
- Net fusion electricity generationTarget 2030Not yet reached.
Upcoming
- Oct 2026Main machine enters four-ring assembly (next)
- Q4 2027First plasma
- Q4 2027First plasma target
- 2028D-T burning plasma experiments begin
- 2030Net fusion electricity generation