Give European researchers and companies a sovereign machine for climate, materials, medicine and large AI models, at more than one exaflop/s in about 15 MW.

ProtoStage 2 of 5

Being built by Eviden for TGCC; delivery in two stages, end of 2026 and 2027; users expected in 2027.

Updated 18 Nov 2025Checked 11 Oct0 updates this week

Milestones

Next · Installation and deployment begin at TGCC
  1. EuroHPC picks Jules Verne consortium to host it20 Jun 2023Complete.
  2. Eviden selected, contract signed at SC2518 Nov 2025Complete.
  3. Installation and deployment begin at TGCCTarget 2026Current milestone.
  4. First delivery stageTarget Q4 2026Not yet reached.
  5. Second delivery stageTarget 2027Not yet reached.
  6. First researchers on the systemTarget 2027+3 mooriginally Q4 2026Not yet reached.

Most important updates

Upcoming

  1. 2026Installation and deployment begin at TGCC (next)
  2. Q4 2026First delivery stage
  3. Q4 2026First stage of Alice Recoque delivered to TGCC
  4. 2027Second delivery stage
  5. 2027First researchers on the system+3 mooriginally Q4 2026
  6. 2027First researchers start using Alice Recoque
Primer