Milestones
- FQ-42A prototype first flight27 Aug 2025Complete.
- USAF awards production contract17 Jun 2026Complete.
- Low-observable paint facility completedJul 2026Complete.
- First operational FQ-42 delivered to test unit18 Sep 2026Complete.
- Production ramps to 6 aircraft per monthTarget 2026Current milestone.
- Operational service with USAFTarget 2027Not yet reached.
Most important updates
- First operational FQ-42A delivered to USAF test unit at Creech AFB23d ago
- General Atomics completes low-observable paint facility for FQ-42 productionJul 2026
- U.S. Air Force awards FQ-42A production contract four months ahead of schedule17 Jun 2026
- General Atomics FQ-42A Vengeance makes first flight27 Aug 2025
Upcoming
- 2026Production ramps to 6 aircraft per month (next)
- 2027Operational service with USAF
- 2027Initial operational capability