Snowy Hydro adds fourth tunnel borer to keep project on track
Snowy Hydro deployed a fourth tunnel boring machine (Monica) to accelerate underground work on Snowy 2.0. The project is over 70% complete with first power targeted for H2 2027, though cost has exceeded A$12B.
- Fourth TBM added after hard rock and faults slowed initial progress.
- Snowy 2.0 will deliver 2.2 GW and 350 GWh storage across 37 km of tunnels.
- First power now targeted for H2 2027, a six-year delay from 2021.
- Cost grew from A$2B (2017) to over A$12B due to geological complexity.