Project Crucible (Clarksville smelter)

by Korea ZincKR

Give the US its first new zinc smelter since the 1970s and a domestic source of critical by-product metals that today come mostly from China.

ProtoStage 2 of 5

Site work under way; environmental review cleared Sep 2026; main construction from 2027.

Updated Sep 2026Checked 11 Oct0 updates this week

Milestones

Next · Site preparation and engineering
  1. Deal with US Departments of War and Commerce announced15 Dec 2025Complete.
  2. Project officially launched in Clarksville1 Apr 2026Complete.
  3. First project designated under FAST-41 permittingApr 2026Complete.
  4. Final environmental assessment: no significant impactSep 2026Complete.
  5. Site preparation and engineeringTarget 2026Current milestone.
  6. Main construction begins (about 33 months)Target 2027Not yet reached.
  7. Phased commercial operations beginTarget 2029Not yet reached.
Primer